top of page

SFWMD

S-319 GENERATOR REPLACEMENT AND RELOCATION

S-319 GENERATOR REPLACEMENT AND RELOCATION

The project consists of replacing and relocating the existing generators into two new generator buildings adjacent to the existing pump stations. It includes upgrading automatic and manual transfer switches for a more reliable emergency and backup power source at both pump stations. Work is to progress in stages, such that, new equipment is to be installed, tested, and energized before existing equipment is de-energized and removed.

OWNER

South Florida Water Management District

DESIGN TEAM

Architects International

LOCATION

Martin County, FL

Browse Projects

bottom of page