Owner: 
Miami-Dade Transit
Design team: 
Nifah & Partners
Delivery method: 
Design-Build
Location: 
Hialeah, FL

The proposed improvements on this project focus on the Lehman Center Test Track/Lehman Yard Rehabilitation Expansion, Phase 1. Some of the specifics include the design, permitting and construction of a test and siding track, inspection building, five (5) new storage tracks and two (2) maintenance-of-way tracks. The scope also comprises the implementation of a train control and communication system house, closed circuit television (CCTV), telephone systems and traction power connection along with the addition of track switches, controlled by the existing control building at the yard tower.